Variations in Construction Contracts

Facebook
Twitter
LinkedIn

Variations in construction contracts are changes or adjustments to the original scope of work. These can occur due to unforeseen circumstances or specific needs arising during the project’s execution. Variations could involve changes in the design, the quantity of work, or the type of materials to be used. They can also involve extending or reducing the timeline or altering the way certain tasks are to be performed.

A variation in construction contracts refers to any change or modification to the original contract scope, including adjustments to the design, materials, quantities, sequence of work, or execution methods. These changes can arise due to unforeseen conditions, client requests, regulatory changes, or site constraints.

Variations are a natural part of construction projects, as it is often difficult to account for every scenario at the planning stage. They may arise from changes in the Employer’s requirements, issues with the site conditions, or design modifications. It is important for the contract to have a well-defined process for handling variations, including how they are requested, documented, and priced. Without proper procedures, variations can lead to disputes over cost, schedule, and performance.

For more please see: Variations and Performance Security


Importance of Variations in Construction Contracts

Flexibility in Project Execution: Allows for modifications due to design evolution, unforeseen conditions, or compliance requirements.

Risk Management: Ensures that project stakeholders can fairly allocate and manage risks related to changes.

Cost and Time Adjustments: Enables fair compensation for contractors when changes affect costs or project timelines.

Quality and Compliance Assurance: Ensures that the project meets updated standards or regulatory requirements.

Dispute Prevention: Provides a structured approach to handling changes, reducing conflicts between parties.


Causes of Variations in Construction Projects

Variations can occur for a variety of reasons, some of which may be beyond the control of the parties involved. The most common causes of variations include:

Design Changes: Sometimes, the Employer may request modifications or additions to the design during the course of the project. These changes might be driven by shifts in the project’s goals, new technologies, or updated regulations.

Unforeseen Site Conditions: Unexpected issues such as poor soil conditions, hidden structural defects, or weather-related challenges may necessitate changes in the original scope of work.

Errors or Omissions in the Contract Documents: If the initial design or specifications contain errors or omissions, corrections may be needed that affect the scope of work.

Employer’s Requests: The Employer may request additional works or changes to the project scope, such as adding new features or materials.

Regulatory Changes: Changes in laws, regulations, or safety standards during the course of the project might require modifications to the original contract scope.


Variations Under FIDIC Contracts

The FIDIC (Fédération Internationale des Ingénieurs-Conseils) contracts provide specific provisions regarding variations. The most relevant clauses include:

Clause 13 – Variations and Adjustments

This clause allows the Employer or Engineer to initiate changes in the contract. Key points include:

Clause 13.1: Right to Vary – The Engineer (under the Red and Yellow Books) or the Employer (under the Silver Book) has the right to instruct variations.
Clause 13.2: Value Engineering – Encourages the contractor to propose beneficial changes that reduce costs or improve efficiency.
Clause 13.3: Variation Procedure – Defines the process of issuing and confirming variations.
Clause 13.4: Payment for Variations – Outlines how variations impact contract price and payment mechanisms.

Clause 12 – Measurement and Evaluation

Relevant for re-measurable contracts, ensuring fair valuation of additional or reduced works.

Clause 8.4 – Extension of Time (EOT) for Variations

Ensures that if a variation impacts the completion date, the contractor is entitled to an extension.


Managing Variations in FIDIC Contracts

Clear Documentation – Variation orders should be well-documented to avoid disputes.
Proper Authorization – Variations should be formally approved as per contract requirements.
Cost and Time Analysis – Every variation should be assessed for its impact on the project budget and schedule.
Dispute Resolution Mechanisms – If disagreements arise, FIDIC provides a structured dispute resolution process (Clause 20 – Claims and Disputes).


Conclusion

Variations are an essential aspect of construction contracts, ensuring flexibility, fairness, and quality control. The FIDIC framework provides a clear mechanism for managing variations, protecting both employers and contractors while maintaining project efficiency.

Leave a Comment

Your email address will not be published. Required fields are marked *

এই লেখকের অন্যান্য লেখা

FAQ

অডিট আপত্তি: “ভ্রমণ ভাতা”

সরকারি ক্রয় নিরীক্ষা (Procurement Audit) সরকারি নিরীক্ষা (Government Audit) এর একটি অবিচ্ছেদ্য অংশ। প্রায় প্রতি বছরই প্রতিটি সরকারি দপ্তরে এই

Read More »
Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
গ্রাহক হোন

শুধুমাত্র Registered ব্যবহারকারিগন-ই সব ফিচার দেখতে ও পড়তে পারবেন। এক বছরের জন্য Registration করা যাবে। Registration করতে এখানে ক্লিক করুন

 

** সীমিত সময়ের জন্য Discount চলছে।

ফ্রী রেজিস্ট্রেশন

“প্রকিউরমেন্ট বিডি news”, “সমসাময়িক”, “সূ-চর্চা”, “প্রশিক্ষণ” অথবা “ঠিকাদারী ফোরাম” ইত্যাদি বিষয়ে কমপক্ষে ২টি নিজস্ব Post প্রেরণ করে এক বছরের জন্য Free রেজিষ্ট্রেশন করুণ। Post পাঠানোর জন্য “যোগাযোগ” পাতা ব্যবহার করুণ।

সূচীঃ PPR-08

Scroll to Top